{"ok":true,"updated":"2026-11-23","rule":"Every number keeps its own definition, date and source. Figures with different definitions are never added together, and a chart joins only the same measure from the same source.","totals":{"grids":6,"utilities":3,"figures":36,"newest":"2026-11-05"},"grids":[{"slug":"ercot","name":"ERCOT","url":"https://siscto.si/queue/ercot/","figures":12,"headline":{"id":"ercot-req-2606","series":"ercot-requests","kind":"requests","label":"Large load interconnection requests","def":"Large loads seeking interconnection, as of June 2026. ERCOT says about 90% are data centers. This is the last count of the old process, which ended on July 10, 2026.","mw":474000,"approx":true,"as_of":"2026-06-30","as_of_text":"June 2026","source":{"publisher":"ERCOT","title":"ERCOT update to the Texas Senate, July 29, 2026: Assessing the grid","url":"https://www.ercot.com/files/docs/2026/07/29/ERCOT-Senate-July-29-Panel-1-Assessing-The-Grid.pdf","date":"2026-07-29","read":"2026-11-23"}}},{"slug":"pjm","name":"PJM","url":"https://siscto.si/queue/pjm/","figures":4,"headline":{"id":"pjm-dc-2030","series":"pjm-dc-growth","kind":"forecast","label":"Data center growth PJM's review supports, 2025 to 2030","def":"PJM's own reading of utility requests and national projections: \"Supports PJM data center growth of up to ~30 GW between 2025 and 2030.\" A forecast, not requests.","mw":30000,"approx":true,"as_of":"2025-11-24","as_of_text":"November 24, 2025","source":{"publisher":"PJM","title":"Load Adjustment Requests Summary for the 2026 Load Forecast, Load Analysis Subcommittee","url":"https://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/las/2025/20251124/20251124-item-03---large-load-adjustment-requests-summary.pdf","date":"2025-11-24","read":"2026-11-23"}}},{"slug":"miso","name":"MISO","url":"https://siscto.si/queue/miso/","figures":7,"headline":{"id":"miso-epr-2026","series":"miso-epr-2026","kind":"studied","label":"Projected for 2026 (17.8 GW approved, 8.6 GW proposed)","def":"MISO's projection for its 2026 planning cycle (MTEP26) as of July 8, 2026: 17.8 GW already approved plus 8.6 GW of additional proposed load, a total MISO states itself. Kept off the yearly line because part of it is still proposed.","mw":26400,"approx":false,"as_of":"2026-07-08","as_of_text":"July 8, 2026","source":{"publisher":"MISO","title":"MISO Status Update to the Missouri Public Service Commission","url":"https://psc.mo.gov/CMSInternetData/Agenda%20Presentations/2026%20Presentations/8-19-26%20MISO%20Status%20Update.pdf","date":"2026-08-19","read":"2026-11-23"}}},{"slug":"spp","name":"SPP","url":"https://siscto.si/queue/spp/","figures":2,"headline":{"id":"spp-hill-mo-req","series":"spp-hill-mo","kind":"requests","label":"HILL requests in Missouri","def":"Total load of the 11 High Impact Large Load requests in SPP's Missouri area (7 in one path, 4 in the other). Missouri only, not all of SPP.","mw":3871,"approx":false,"as_of":"2026-08-19","as_of_text":"August 19, 2026","source":{"publisher":"SPP","title":"SPP Status Update to the Missouri Public Service Commission","url":"https://psc.mo.gov/CMSInternetData/Agenda%20Presentations/2026%20Presentations/8-19-26%20SPP%20Status%20Update.pdf","date":"2026-08-19","read":"2026-11-23"}}},{"slug":"nyiso","name":"NYISO","url":"https://siscto.si/queue/nyiso/","figures":3,"headline":{"id":"nyiso-q-2605","series":"nyiso-queue","kind":"requests","label":"Large load projects in the interconnection queue","def":"51 large load projects in the queue as of May 1, 2026, which would add nearly 12,670 MW of load.","mw":12670,"approx":true,"as_of":"2026-05-01","as_of_text":"May 1, 2026","source":{"publisher":"NYISO","title":"Power Trends 2026","url":"https://www.nyiso.com/documents/d/guest/2026-power-trends","date":"2026-06-07","read":"2026-11-23"}}},{"slug":"southeast","name":"Southeast","url":"https://siscto.si/queue/southeast/","figures":2,"headline":{"id":"so-contracts-2609","series":"so-reviewed","kind":"contracted","label":"Southern Company: large load contracts reviewed by the state commissions","def":"Contracts since 2023 with new data centers and other large load customers, each over 100 MW, reviewed by the applicable state public service commission.","mw":16000,"approx":true,"as_of":"2026-09-30","who":"Southern Company","as_of_text":"September 30, 2026","source":{"publisher":"Southern Company","title":"Quarterly report for the quarter ended September 30, 2026 (SEC Form 10-Q)","url":"https://www.sec.gov/Archives/edgar/data/92122/000009212226000069/so-20260930.htm","date":"2026-11-05","read":"2026-11-23"}}},{"slug":"aep","name":"American Electric Power (AEP)","url":"https://siscto.si/queue/#utilities","figures":6,"headline":{"id":"aep-2610","series":"aep-2031","kind":"contracted","label":"Contracted load by 2031","def":"After 15 GW of new load commitments in the third quarter of 2026. AEP moved the horizon to 2031, so this figure is kept off the 2030 line.","mw":84000,"approx":false,"as_of":"2026-10-28","as_of_text":"October 28, 2026","source":{"publisher":"AEP","title":"Third-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)","url":"https://www.sec.gov/Archives/edgar/data/4904/000000490426000069/a3q20268kpressreleaseex991.htm","date":"2026-10-28","read":"2026-11-23"}}}],"url":"https://siscto.si/queue/"}